
$450,000 Fine After Forklift Runs Over 18-Year-Old Worker: What Employers Must Know About Workers Compensation Liability
March 18, 2026
The $2.5 Million Handbrake: What This Queensland Case Reveals About Safe Systems of Work
March 18, 2026Most construction managers running projects under 30 workers do not have a dedicated WHS management team. That does not change the legal obligation. Under the Work Health and Safety Act 2011, the duty to manage subcontractor WHS compliance sits squarely with the PCBU running the project, regardless of how many people are on the payroll or whether a full-time safety professional is present.
This guide covers exactly what subcontractor WHS management looks like in practice when the construction manager is doing the job themselves, or supported by an external WHS consultant one day per week.
The Legal Position: You Cannot Contract Out Your WHS Duties
The most important thing to understand about subcontractor WHS management is that engaging a subcontractor does not transfer your WHS obligations to them.
Under Sections 14 and 272 of the WHS Act, WHS duties are non-transferable. A PCBU cannot contract out its duty of care to another party in the contractual chain. This applies regardless of what your subcontract agreement says.
Key principles from the Safe Work Australia WHS Duties in a Contractual Chain Fact Sheet:
- WHS duties are not transferable between parties in a contractual chain
- WHS duties cannot be contracted out to a subcontractor
- A person can hold more than one duty simultaneously (a subcontractor is both a PCBU and a worker)
- There does not need to be a direct contractual relationship between a head contractor and a subcontractor’s worker for a duty of care to exist
- The more control a PCBU exercises over work, the greater the responsibility to discharge the shared WHS duty
- All PCBUs in the chain must consult, cooperate, and coordinate with each other on WHS matters
- Each subcontractor must manage risks arising from their own work so far as is reasonably practicable
- Every subcontractor must be aware of the WHS management plan and comply with site safety rules
- Head contractors must check subcontractor work procedures even where work is fully subcontracted
- Principal contractors on projects over $250,000 must obtain SWMS for all high-risk construction work before it begins
What Triggers the Principal Contractor Role
The principal contractor role is triggered by the project value threshold, which varies by state:
| State / Territory | Project Value Threshold |
| NSW | $250,000 |
| QLD | $250,000 |
| WA | 6 people or more |
| VIC | $250,000 |
| SA | $450,000 |
| ACT | $250,000 |
| TAS | $250,000 |
| NT | $500,000 |
Below these thresholds, the principal contractor obligations under Part 6.4 of the WHS Regulations do not formally apply. However, the primary duty of care under Section 19 of the WHS Act applies to every PCBU at every project value. Subcontractor WHS management is not optional on a $150,000 project.
For a full breakdown of principal contractor obligations by jurisdiction, see WHS Harmonisation in Australia on HSE Direct.
The Five-Step Subcontractor WHS Management System for Small Construction Businesses
This is a lean, practical system that a construction manager can operate without a dedicated WHS officer. It covers prequalification, documentation, induction, monitoring, and review.
Step 1: Prequalification Before You Engage
Before any subcontractor sets foot on site, verify the following. Document the results and keep them on file.
Prequalification checklist for each subcontractor:
| Requirement | What to Verify | Record |
| Public liability insurance | Minimum $10m, current certificate of currency | Copy of certificate |
| Workers compensation | Current policy or exemption letter | Copy of policy |
| WHS licences and tickets | White Card, high-risk work licences (HRWL) relevant to scope | Copy of licences |
| SWMS capability | SWMS for all high-risk construction work in their scope | Obtain before engagement |
| ABN and business registration | Confirms PCBU status, not sham contracting | ABN lookup |
| Previous WHS incidents | Ask directly, check ASIC / public records for prosecutions | Record responses |
A subcontractor who cannot provide a current certificate of public liability insurance, workers compensation, and relevant HRWL tickets before mobilising is a compliance risk and a legal exposure. Do not start work.
For prequalification templates, visit HSE Direct WHS Resources.
Step 2: SWMS Collection and Review
Under WHS Regulations Part 6.3, Division 2 (Regulations 299-302), a SWMS is required for every high-risk construction work (HRCW) activity. As the principal contractor or head PCBU, you must collect and review each subcontractor’s SWMS before that work begins.
High-risk construction work requiring a SWMS includes:
- Work at a height where a person could fall more than 2 metres
- Work in or near a confined space
- Work involving demolition
- Work near or involving live electrical services
- Work involving excavation deeper than 1.5 metres
- Work on or near pressurised gas distribution systems
- Work involving asbestos
- Work with structural alterations requiring temporary support
Reviewing a SWMS does not mean rubber-stamping it. The review must confirm the SWMS actually identifies the hazards specific to your site conditions, lists realistic controls (not generic statements), and is signed by the workers who will perform the work.
A common and legally costly mistake: subcontractors assuming the principal contractor’s SWMS covers their workers. It does not. Every PCBU must have their own SWMS for their own high-risk work.
Step 3: Site Induction
Every subcontractor worker must be inducted into the site before starting work. The induction must cover site-specific information, not generic safety content.
Site induction must include as a minimum:
- Site emergency and evacuation procedures
- First aid locations and first aid officer contacts
- Site entry and exit rules
- Identified site hazards (overhead services, underground services, traffic, proximity hazards)
- Site rules: PPE requirements, speed limits, alcohol and drugs policy
- WHS management plan location and how to access it
- HSR contacts and process for raising WHS concerns
- Incident and near-miss reporting procedure
- Permit requirements (excavation, hot works, confined space, height work)
Keep a signed induction register. If a regulator arrives on site and a worker cannot demonstrate they were inducted, the exposure is yours.
Step 4: Ongoing Site Monitoring
A signed SWMS and a completed induction do not constitute ongoing subcontractor WHS management. The WHS Act requires active, continuing oversight of work being performed.
For a construction manager without a dedicated safety team, minimum monitoring activity includes:
- Daily pre-start verification that SWMS controls are in place before high-risk work starts
- Visual site inspection at least once per shift covering housekeeping, PPE compliance, barricading, and plant exclusion zones
- Random SWMS field checks: cross-reference what workers are actually doing against what the SWMS says
- Immediate stop-work if a subcontractor is operating outside their SWMS or site rules
- Weekly toolbox talk covering current site-specific hazards (15 minutes, signed attendance)
- Permit review each morning for any excavation, hot works, confined space, or height work
The legal test under the WHS Act is “reasonably practicable.” On a project under 30 workers with low to medium risk work, the monitoring described above satisfies that test. On higher-risk work, more structured oversight is required.
For guidance on when your project requires a dedicated WHS resource, see HSE Direct WHS Services.
Step 5: Non-Conformance and Stop-Work
When a subcontractor is found non-compliant, the response must be documented and proportionate.
Non-conformance response procedure:
- Stop the specific activity immediately if it poses immediate risk
- Discuss the non-conformance with the subcontractor supervisor directly
- Record the finding on a site inspection form with date, time, subcontractor name, and description
- Confirm corrective action and timeframe in writing (text message records are acceptable)
- Re-inspect to confirm correction before resuming the activity
- Escalate to SWMS revision if the non-conformance reflects a systemic issue in their method
Repeated non-conformance is grounds for terminating the subcontract. The WHS Act does not require you to continue engaging a subcontractor who will not meet their obligations. Document every step.
Documents You Must Have on Site
This is the minimum documentation set for a construction project under 30 workers managed without a full-time WHS team:
| Document | Who Prepares It | Where Kept |
| WHS Management Plan | Head contractor / principal contractor | Site office, accessible to all workers |
| SWMS for each HRCW activity | Each relevant subcontractor | At the work face during the activity |
| Site induction register | Head contractor | Site office |
| Subcontractor prequalification register | Head contractor | Site office |
| Insurance and licence register | Head contractor | Site office |
| Daily pre-start checklist | Supervisor on site | Site file |
| Incident and near-miss register | Head contractor | Site office |
| Emergency response plan | Head contractor | Posted at site entry and amenities |
| Excavation and ground penetration permits | Permit Authority | At the work face |
Projects above $250,000 must have a written WHS Management Plan before work starts under WHS Regulation 293. Projects below this threshold should still maintain a documented safety management framework. The absence of documentation is the most common aggravating factor in WHS prosecutions.
When One Day Per Week With a WHS Consultant Is the Right Model
For construction projects under 30 workers with a mix of low to medium risk work, a one-day-per-week external WHS consultant arrangement delivers structured compliance without the cost of a full-time hire.
What one day per week with HSE Direct delivers:
- Weekly site inspection with written report and photographic evidence
- SWMS review and sign-off for all active high-risk activities
- Subcontractor prequalification document checks
- Toolbox talk facilitation and attendance record
- Permit system audit
- Regulatory update advice as WHS Regulation 2025 (NSW) changes take effect
- Documented evidence of active due diligence that can be produced to a regulator
At $1,000 per day, 48 working weeks, the full annual cost is $48,000. Compare that to a fully loaded WHS Advisor at $228,000 per annum. For projects under 30 workers where HRCW is managed and low-risk activities dominate, the one-day model is appropriate and legally defensible. For the cost comparison in full detail, see HSE Direct WHS Cost Comparison.
For projects that escalate in risk profile, that arrangement scales up. The model is not fixed.
Regulatory References
All subcontractor WHS management obligations derive from the following legislation and guidance:
- Work Health and Safety Act 2011 (Cth model law): Sections 14, 19, 27, 28, 272, Part 7
- WHS Regulation 2017 (NSW) / 2025 (NSW from 22 August 2025): Part 3.1 (regs 32-38), Part 6.3 Division 2 (regs 299-302), Part 6.3 Division 3 (regs 304-306), Part 6.4 (regs 309-312)
- SafeWork Australia: WHS Duties in a Contractual Chain
- Comcare: Contractor Management Guidance for PCBUs
- SafeWork NSW: Construction Work Code of Practice
- WorkSafe QLD: Managing Safety in the Workplace
- WorkSafe ACT: WHS Management Plans
- Safe Work Australia: Managing Risks
This guide reflects WHS legislation as at March 2026. Regulatory thresholds and specific obligations vary by state. For subcontractor WHS management support, prequalification systems, SWMS review, or weekly site compliance services, contact HSE Direct.
Follow @hse_directon Instagram for WHS compliance updates and practical guidance.
